of CC Meeting of July 22, 2008 by C. Kazanjian “Request that the
In response to the
above-mentioned motion, T.J. McCarthy has provided a report on the two
simultaneous construction projects currently taking place at the
Regarding the boiler project:
Ø
Removed old
boiler
Ø
Poured new
concrete pad
Ø
Currently
re-piping/converting water feeds and exchanges
Ø
Expected delivery
of new boiler by August 15th
Ø
Projected
completion of all work by September 30th
Regarding the roof
replacement:
Ø
Bid and contract
processing completed July 30th
Ø
Crane arrived on
site July 31st, will remain on site for two-three weeks
Ø
Construction supplies
arrived last week, deliveries continue through this week
Ø
Engineering plans
submitted to Building Department for review this week
Ø
Notification of
logistical plans (crane) material storage need to be conveyed to School
Department Officials
Ø
Expected
completion of project some time between August 28th and September 18th,
weather permitting
If you have any questions