Summer 2009 Construction Paving

Several of last year’s construction projects are wrapping up this year with their final paving. Both the Water and Wastewater Utilities continue to improve infrastructure and subsequently these roadways are being restored. In some cases the road is being reclaimed before final paving; in some cases the treatment is a mill and overlay.

The streets listed below are in sequential order as submitted by the contractors. Paving is a weather dependent activity so an exact schedule is difficult to determine. The work is beginning today, July 20, 2009 and continuing until completed, in the order below.

Blossom St., Lundberg St., and Bowden St. are part of the CSO project but will be paved by the Engineering Dept. Lundberg and Bowden will be done in August/September. Blossom St. may need to wait until the spring (depending on remaining work to be done).


CSO Contract 07-01 -Baltazar Contractors w/Brox (July 20 through July 31, 2009)

  • Chippewa (Saratoga to Bowden)
  • Corbett
  • Weed
  • Anderson
  • Stromquist
  • O'Connell
  • Fay
  • Gorham (from Shaughnessy School to Carlisle)


CSO Contract 08-01 - RJV Construction Corp. w/ PJ Keating (July 20 through August 7, 2009)

  • Gorham St from Maple to Shaughnessy School - Initial binder
  • Parker St
  • Nottingham
  • Shaw St
  • Lincoln St at Angle St and under Lowell Connector
  • Prelco Lot easement off of Tanner St.
  • Tanner St at Canada St
  • Canada St
  • Main St
  • Gorham St
  • Chelmsford St (between Liberty and Plain) - Initial binder
  • Chelmsford St (between Liberty and Plain) – Top


Water Utility Main Replacement Program

  • Congress and Robinson, reclaim begins Monday 7/20
  • Boston, Swan, Spencer Sts.
  • Stanley St.
  • Stafford St.
  • Unsworth St.