Minutes for Planning Board on April 19, 2007, 06:30 PM
|
|
City of Lowell -Planning Board
Planning Board Minutes
April 19, 2007 6:30 P.M.
City Council
Chambers, City Hall
City of
Lowell, 375 Merrimack Street, Lowell, MA
Note: These minutes are
not completed verbatim. For further
detail, video recordings are available through the Lowell Telecommunication
Corporation’s website at http://ltc.org.
Members
Present
Thomas Linnehan, Chairman
Joseph Clermont, Vice Chairman
Richard Lockhart, Second Vice Chairman
Jerry
Frechette, Member
Stephen
Gendron, Member
Others
James
Errickson, Associate Planner
Approval of Minutes
Motion:
Motion:
Member
Richard Lockhart motioned and Member Joe Clermont seconded to APPROVE the above
minutes as amended. The motion passed
with three members voting in favor and Members Jerry Frechette and Stephen
Gendron abstaining (3-0-2).
Motion:
Member Joe Clermont motioned and Member
Richard Lockhart seconded to APPROVE the above minutes. The motion passed with all members voting in
favor (5-0).
Motion:
Member
Joe Clermont motioned and Member Stephen Gendron seconded to APPROVE the above
minutes. The motion passed with four
members voting in favor and Member Richard Lockhart abstaining due to his
absence at the meeting (4-0-1).
Public Hearings
Repetitive Petition: 21 Eugene Street
The Lowell Planning Board will review an application
to the Zoning Board of Appeals (ZBA) by Albert Stamp for variances required to
construct a single-family dwelling on the property located at 21 Eugene
Street. On January 22, 2007, the ZBA
took an “unfavorable action” on the previous proposal at that site. In order for the ZBA to consider the merits
of this new application, the Planning Board must consent that the new
application contains specific and material changes from the first
application. The Planning Board will
take this vote at the conclusion of the public hearing.
The
following individuals spoke in favor of the project:
Albert
Stamp (21 Eugene Street, Applicant)
In
Favor:
Albert
Stamp (21 Eugene Street): After the initial application, I reduced the overall
footprint to get side-yard setbacks, removed the garage, and excavated a portion
of rock for safety concerns. So when we
went back for Repetitive Petition to the ZBA, they approved.
The
following individuals spoke in opposition of the project:
None
In Opposition:
None
General Discussion:
J.
Clermont: One question. The new plan, revised Jan 31, 2007 noted a smaller
setback. This new proposal has no
garage.
Albert
Stamp: Yes, just a dwelling
R.
Lockhart: You changed the architecture to more conform to the neighborhood?
Albert
Stamp: Yes, to be more consistent with neighborhood.
J.
Frechette: My thoughts, clearly, when looking at concerns from ZBA, the
dimensions were changed for setbacks, and the concerns for ledge were looked
into. The design is much more pleasing
than the original. I believe there are
material and substantial changes.
S.
Gendron: Can I get an explanation on the process for Repetitive Petition?
T.
Linnehan: For this process, this needs to be approved from the ZBA, and comes
to us. If they don’t approve this.
S.
Gendron: I don’t see the ZBA showing concern over the undersized lot. The vote before us is to determine if there
are substantial changes to the design.
I don’t think the changes are substantial enough. But since the ZBA determined this, I feel a
little limited in what we can do.
J.
Clermont: When this matter goes back before the ZBA one the merits, it will
come back before us for the merits of the case.
T.
Linnehan: One of the concerns the first time was the size of the big rock. That is not there anymore.
Albert
Stamp: We tested the ground, and this is going to require heavy equipment to
remove. It was dug out.
T.
Linnehan: Even the property to the
right in the neighborhood is yours?
Albert
Stamp (21 Eugene Street): Yes. It is
deceiving. At one point I had to
purchase a sliver of the land. It is
deceiving.
J. Clermont: Given the change in side yard setback,
the overall footprints, the concern over ledge has been alleviated. Motion to consent to applicant.
Motion:
Considering the merits of the presented materials, the Board consented that the new application provided material and substantial changes from the original application. The Board moved to grant the Repetitive Petition application.
The motion was made by Member Joseph
Clermont and seconded by Member Richard Lockhart. The motion passed with all members voting in favor (5-0).
Site Plan & Special Permit: 672-674
Chelmsford Street
The Lowell Planning Board will review an application
by Daniel and Cindy Sacco for site plan review and special permits for the
development of the property located at 672-674 Chelmsford Street. The proposal includes the construction of
two, three-bedroom units onto the back of an existing two-unit residential
structure with associated landscaping and parking. The proposal is located on an 11,559 sqft lot in the TMU
(Traditional-Neighborhood Mixed Use) Zoning District and requires Special
Permit review under Section 9.4 and Article XII and Site Plan review under
Section 11.4 of the Lowell Zoning Ordinance.
The
following individuals spoke in favor of the project:
Ted
Doucette (Polaris Engineering, Applicant’s Engineer)
In
Favor:
Ted
Doucette (Polaris Engineering, Applicant’s Engineer) Here before with two
different application proposals. One
proposal included two buildings that did not meet zoning. We chose to extend the building. Applicant met with neighbors, and heard no
complaints. Chelmsford Street is here. The existing building is here; the new
structure is here, parking underneath and 6 on the lot for 8 total. We have proposed landscaping that is
designed to screen parking. Some PB
comments before is to match architecture.
We have done this. Existing
building here. Both include the bump
out gables. One of the comments from
the DPD is to make sure the siding matches to create a continuous
building.
The
following individuals spoke in opposition of the project:
None
In Opposition:
None
General Discussion:
R.
Lockhart: Question relative to density.
The material we have, are there opportunities to buffer?
Ted
Doucette (Polaris Engineering, Applicant’s Engineer): I was speaking with staff
today, and we can definitely work together.
There are no definitive plans to do anything now, the neighbor would
like to see this tree come down. We are
open to putting some shrubs back here.
The applicant will like to place more trees here.
R.
Lockhart: How about lighting?
Ted
Doucette: We are putting some by the garages.
R.
Lockhart: There were some questions from the engineer regarding testing the
soils?
Ted
Doucette: yes, we have been waiting for the weather to be better. We know we need to do some testing.
S.
Gendron: I have some concerns about this project. The character of the neighborhood. I feel as though adding two more units in this neighborhood is
detrimental to character. Down on Newal
Street with single family, and allowing this development we are setting a
precedent to do this type of project.
So that is my primary concern.
Getting in and out of that driveway is a challenge. That may be a traffic problem.
J. Frechette: Just the design of the building, if you
could go over the height of the building in relation to the neighborhood. Is it possible to lower the slope of the
roof to match the existing building?
Ted
Doucette: I recall the conversation of the rooflines. We have it close, but we can definitely look at this to try to
address the Board’s concerns.
J.
Frechette: The concern is the screening of the parking from the roadway. Right now, that is more green space that
should be used, so one does not look at a parking lot.
Ted
Doucette: These shrubs that exist and are 6 feet high. I think they are better than trees, and we
can address these in talking about the landscaping.
J.
Clermont: just a few, on your plans, the bump outs, does that provide living
space?
Ted
Doucette: that is going to be for living space.
J.
Clermont: and you are going to add the gables?
Ted
Doucette: yes, the owner will add the gables.
J.
Clermont: will that be living space in the attic?
Ted
Doucette: no that will not be living.
The old are 2 bedroom units, and the new are 3 bedroom units.
J.
Clermont: did the fire department review the plans?
Ted
Doucette: I spoke with Captain Weber and he referred me to the fire code. I also spoke with the water department, and
he wants me to complete the plans at once and then come back.
J.
Clermont: I’d like to see comments from the fire department for safety
concerns. And the traffic engineer
noted the need to screen the cars from the roadway view. Can you point out the trees to be taken
down?
Ted
Doucette: the maple tree here, and the pine tree here. The neighbor requested to take down the
pine.
J.
Clermont: we are not hearing any opposition, but it would be nice to see
vegetation along the back portion of the lot.
The location of the utility meters, where will they be?
Ted
Doucette: there is space for them in the front with landscaping.
J.
Clermont: and the retention system will need an easement for the City.
T.
Linnehan: did you review the note from the engineer? He noted the underground detention system. If a system cannot be put in, he recommended
that the units should not be built.
Ted
Doucette (Polaris Engineering, Applicant’s Engineer): Yes, I can do that. Will that be a decision or a condition of
approval?
T.
Linnehan: Well, that is up to the Board, we usually don’t see that strong
wording. The plan itself, we talked
about the preliminary plans. I think my
mind has changed, and I think this is a better layout. It has less of an impact on the neighborhood. From the street now, it won’t look that
different. If you are going to side it,
side the entire building. You indicated
that you would do this, which is good for appearance sake. James can you elaborate on the landscaping?
J.
Errickson: yes, I wanted to make sure the Board was aware of the loss of
vegetation and landscaping, and the possible need to add additional
landscaping.
T.
Linnehan: thank you. If those trees
came down, would you be wiling to have new ones planted?
Daniel
Sacco: yes absolutely.
T.
Linnehan: I think you can add some landscaping that will address the neighbor’s
desires, but add some landscaping. We
have approvals from wastewater, traffic engineer. Comments from city engineer.
Missing from Fire and water departments.
J.
Clermont: approve: given lack of opposition, vote to approve with conditions.
Motion:
The site plan and special permit were approved with
the following conditions:
- The applicant must receive an affirmative comment from the
Fire Department, and/or address comments necessary to achieve approval
from the Fire Department.
- The
applicant must receive an affirmative comment from the Water Utility
Department, and/or address comments necessary to achieve approval from the
Water Utility Department.
- The
applicant must address the comments made by the City Engineer, and
incorporate necessary changes to the plans to receive an affirmative
comment from the City Engineer.
- The applicant must
develop a building façade that appears as one building, so as to not
project the appearance of a new building being attached to an existing
structure. This may be
accomplished in the form of re-siding and/or painting the entire finished
structure.
- No utility
meters, including electric, water and/or gas meters, shall be located in
any location visible from Chelmsford Street. If utility meters are located in such areas, they must be
properly landscaped so as not to be visible from Chelmsford Street.
- The
applicant must create an easement to the site to allow the City to access
the drainage system in the event of an emergency. The City of Lowell will have permission
to enter the site, repair the drainage system and charge the owners on the
site, in the event that the drainage system fails and is not repaired by
the condominium association.
- The
applicant must work with the DPD design planner on a final landscaping
plan for the site.
The motion to approve the site plan and special permit was made by
Member Joseph Clermont and seconded by Member Richard Lockhart. The motion passed with four members voting
in favor, and Member Steven Gendron voting in opposition (4-1).
Site
Plan: 812 Gorham Street
The
Lowell Planning Board will review an application by Watermark Engineering and
the City of Lowell School Department for site plan review for the development
of a the property located at 812 Gorham Street. The proposal includes the renovation of a late nineteenth century
Butler Elementary School and the new construction of two educational wings. Parking for the facility will consist of 24
spaces in two parking areas with access off Ellsworth Street and Carter
Street. The proposal is located on a
59,000sqft lot in the TMU (Traditional-Neighborhood Mixed Use) Zoning District
and requires Site Plan review under Section 11.4 of the Lowell Zoning
Ordinance.
The
following individuals spoke in favor of the project:
John Haley (Watermark Engineering), Architect, Francis King (26Livingston Street), Mark Goldman (58 Oakland Street)
In
Favor:
John
Haley (Watermark Engineering) Jay Langley (school department), Francis King (26
Livingston Street), Mark Goldman (58 Oakland Street) the architect. Been including all departments throughout
the design. We are currently in the bid
page for both projects. Once the bit
pricing comes in, the city council will determine whether the schools will be
constructed. That bidding process ends
next Wednesday. There are many actions
that have not been taken care of yet until the vote from the City Council. Once that vote is taken, we will involve the
neighborhood for this project.
Architect for School: We do have a model up
here. The original building is this
center building here. We are adding on
two wings. The right side is classrooms,
specialty classrooms. Existing will be fully restored with general classrooms. Excavating here for a lower level to open to
grade. The goal is to create modest
renderings to create two additions to the existing buildings. The new additions will be lower than
existing building to keep scale down.
Plan to keep buildings as far forward as possible. Reach balance of new flanking existing. Keep clear of residents around the
site. Creating new bus drop off Gorham
Street, with a planting buffer between access point and Gorham Street. Two parking, one across the street for staff,
and one on site. Parent drop off, will
be around the rear, to keep busses and parents out of conflict from each
other. Interior, reusing some space for
storage. Administration and gym to
right, class rooms in center, and specialty rooms in center.
Francis
King (26 Livingston Street): Owns company with access from Livingston
Street. I have some concerns here; this
is the first I have seen of the drawing.
Livingston is a narrow street. I
am in the waste removal business.
Employ 15 people. See how this
project will have an impact on me. I am
not here to stop this project. It’s a
pleasure to see that this school will be renovated. There are concerns, about
parking, how can I live and the neighbors live with the school. Will there be on street parking for school
personnel? Where do I move my people to
park? Street width on Livingston, is
difficult, are there adjustments in that area?
Mark
Goldman (58 Oakland Street): it is a great mix of renovating the old school and
making the additions compatible to the buildings. I am in favor of the project.
Are there going to be any outside space for school children to play in?
The
following individuals spoke in opposition of the project:
None
In
Opposition:
None
General
Discussion:
T.
Linnehan: How is the structure of the existing building?
Architect
for School: We had an engineer review integrity of buildings. There has been water damage. But that has not affected the
structure. There may be other
questions, but they will be addressed during construction.
J.
Frechette: If you could go over the parent drop-off? And taking into account
Mr. King’s questions, and how it all addresses parking.
Architect
for School: Parent drop-off, we had several meetings with the school department
and the city to come up with the best solution to access the building. It was determined that all the busses and
delivery vehicles would be off of the main drive. Only passenger cars will be on Livingston. The parent drop off is here in the back of
the building.
J.
Frechette: can you discuss the parking, and in regards to the interior floor
plan.
Architect
for School: there are 16 general classrooms, and 4 others, so there are 20
classrooms. And there is the need for 3
parking for every 2-classrooms. And
there are 24 parking spaces.
John
Haley: there are other city owned lots around the area, and the parking needs
will need to be met before the project continues.
Architect
for School: there is a hard surface play area here, and soft surface play area
here, and a gymnasium. It is a very
tight site.
J.
Frechette: I appreciate the visual look, and fitting in the new wings.
John
Haley: there will be some additional roadway improvements on Livingston.
S.
Gendron: We don’t want to delay
anything to get state funding. In its
current state, the parking seems woefully insufficient. And I think it would be a good idea to have
a condition to have additional accommodations to be made for the project. Is that a regulation gym?
Architect
for School: The state actually regulates gym size. So it is similar to other junior highs.
S.
Gendron: How about the bleachers?
Architect
for School: Yes, the bleachers are designed for both a game and an
assembly. And they are electronically
operated.
S.
Gendron: currently, is the back entrance used to get in and out of the
building?
John
Haley: There is an access way to get into the basement, but the primary
entrance is the front of the building.
R.
Lockhart: I think, looking at the site, it is a tight lot. In my opinion, the fact that the play area
is needed to be larger. And did you say
that the facility will be serviced through the front door?
Architect
for School: No, the service uses this roadway, but the supplies are dropped off
here. The issue was the access off Livingston
is not adequate.
R.
Lockhart: can you address Mr. King’s concern?
Architect
for School: not any more that what we have already noted. There will be more traffic there, since the
school is not being used there now.
Busses and trucks will not use Livingston Street.
R.
Lockhart: have you worked with historic board personnel on this? It is an historic building.
Architect
for School: yes.
John
Haley: they were hoping that the new windows match the old style.
R.
Lockhart: can you address the engineer’s comments?
John
Haley: Yes, we will address those concerns if we proceed with this school
further.
J.
Clermont: can you point out what portions of the project need to acquire land?
John
Haley: there is a parking lot here, and the design was moved forward. There are some properties that have
encroached on the City property. But we
are not taking any land. The city owns
a significant piece of land behind the area here; we can look at these parcels.
J.
Clermont: Has there been a traffic study for this project?
John
Haley: no, we have just accounted for parking.
J.
Clermont: the engineer has had a number of comments.
John
Haley: yes, the new plans have addressed those concerns.
T.
Linnehan: We have received conservation, health, water, and engineer all in
approval. Do you know how many students
are going to be here? And employees?
Architect
for School: the school is designed for 550 students, and 75 employees.
T.
Linnehan: would you consider having faculty park off site, and keep visitor
close to the building?
John
Haley: yes that is our intent.
T.
Linnehan: When we have had projects before us with the schools. Usually we have the whole site plan before
use. If we did give this a favorable
reply, if you could show us a full plan in the future, maybe as a condition of
approval.
Motion:
The site plan was approved with the following
conditions:
- The applicant must
apply for and receive any and all required variances for the project,
including those necessary for the construction of the access drive to the
school site off of Gorham Street.
- The applicant must
incorporate all of the City Engineer’s comments from memo dated March 28,
2007. An updated set of plans must
be reviewed and approved by the City Engineer.
- The applicant must
provide adequate parking for the project site, as required under Section
6.1.4 of the Lowell Zoning Ordinance, requiring “3 parking spaces for
every 2 instructional rooms.”
- The applicant must
present to the Planning Board at a regularly scheduled public meeting any
modifications from the current plans that add new parking areas or alter
the layout of the proposed parking areas servicing the school.
- The applicant must
complete a traffic study for the proposed school project, which must
provide suggested modifications with regards to Livingston Street. In the event that a traffic study
cannot be provided, the applicant must work with DPD’s Transportation
Engineer to review the proposed project, conduct any necessary traffic
studies, and incorporate any and all of his comments regarding traffic
mitigation around the project site and on Livingston Street into a final
set of plans.
The motion to approve the site plan was made by Member Joseph
Clermont and seconded by Member Richard Lockhart. The motion passed with all members voting in favor (5-0).
Site Plan: 108 Pine Street
The
Lowell Planning Board will review an application by Watermark Engineering and
the City of Lowell School Department for site plan review for the development
of a the property located at 108 Pine Street.
The proposal includes the construction of a new two-story elementary
school building and demolition of the existing three-story brick elementary
school building. Parking for the
facility will consist of 73 parking spaces in two parking areas with access off
Wilder Street and Morey Street. The
proposal is located on a 124,000sqft lot in the TSF (Traditional-Neighborhood
Single-Family) and TTF (Traditional-Neighborhood Two-Family) Zoning Districts
and requires Site Plan review under Section 11.4 of the Lowell Zoning
Ordinance.
The following individuals
spoke in favor of the project:
John Haley (Watermark
Engineering), Architect, Mark Goldman (58 Oakland Street), James Plazas (561
Wilder Street), Sandy & Kevin Courchene (31 Morey Street), Kim & Steve
Layte (25 Morey Street), Issa & Joyce Ansara (21 Morey Street), Donna Cox
(41 Morey Street), Ray Toomajanuan (5 Light Avenue)
In Favor:
John Haley (Watermark Engineering): Morey School here has the same timeline with bidding. It is more than likely that if one school will proceed it is the Morey School. The primary concern here is in regards to the park. It will be utilized during construction. The new school will be used during construction. The park will be designed in the future. If this school does proceed is to meet with the current teachers, students and parents. At this point in time, we have not done this. We do have a phasing schedule.
Architect for School: We are taking down an
existing building, but keep it operating while the new building is
constructed. From a site plan stand
point, this is why the school is cited where it is. Here the building is a two-story building. The height is lower than existing building,
with a large green space in front of it.
We have tried to articulate the end of the buildings, so it is the
similar width of the existing houses to scale the building with the houses on
the street. The exterior will be a
combo of brick and concrete block. Also
using some metal panels, to create a pattern similar to clapboard or
surrounding houses. We tried to
separate bus and parent drop off. Curb
cuts for buss off Pine. Parent drop off
is off morey street. Interior: the main
level has cafeteria. There is plenty of parking. Administration is by the main entry. Gym is in center of building.
Classrooms flank each side. Down
one level are more classrooms and gymnasium, with access off Wilder.
Sandy Courchene (31 Morey Street): I live in
neighborhood. Good project. Glad to see open space.
Steve Layte (25 Morey Street): concerns as to
how close the building will be to our houses.
In the original plans, we had the café, service, and dumpster close to
our house. And we are concerned about
this. Parking during construction, how
will this be handled?
Donna Cox (41 Morey Street): In Favor of the school. During school hours, Morey Street is one
way. But teachers exit parking now, but
will it continue to be one way. Other
question, do we have plans for the park.
Last question, heavy equipment, will that prohibit use of park as it is
right now?
Joyce Ansara (21 Morey Street): have problem
with vandalism, with gangs, dealing drugs.
What are they going to do with rest of property where park is now, where
the basketball court is now?
James Plazas (493 Wilder Street): what is the
distance between this house and the school.
Are there going to be windows on that side of the school?
Ray Toomajanuan (5 Light
Avenue): I have concerns about the park.
One of the dirtiest parks there is, and what will happen with the park?
John Haley: The intent with
the park, is that it will be taken over for the construction. After the park will be replaced, in concert
with the parks department and it will become an elementary park.
The following individuals
spoke in opposition of the project:
None
In Opposition:
None
General Discussion:
S. Gendron: compliment neighbors coming out
tonight. What happens during
construction for parking and play area?
John Haley: The front area here, is not going to be parking lot until this is complete. This will be the play area, and will be available. The entire park will become a parking lot, and the existing park will not be used except for parking and heavy equipment.
S. Gendron: With regards to the park, I
really think this is an opportunity to change that park. How many classrooms?
Architect for School: There are 20, and 30
parking spots.
S. Gendron: can you discuss the parking?
Architect for School: There are 20 classrooms, and the requirement
is for 30 spaces or 3 spaces per 2 classrooms.
S. Gendron: can you discuss the house on
Wilder Street?
Architect for School: yes, there is a
required 10 feet distance here, and the side of the building will have no
windows. The building is 25.5 feet
high, to top edge. It is substantially lower than it is now.
S. Gendron: We are going to continue to have
Morey Street to be one way?
Architect for School: the circulation will be going on a certain
direction, and there was discussion about this, but I don’t think this is
resolved.
S. Gendron: are you going to keep the
neighborhood informed?
John Haley: Yes, we intend to do so.
J. Frechette: can you go through the drop off
area again?
Architect for School: Sure, buses turn off
Pine and exit Wilder. Cars would come
this way, off Morey.